We've strengthened our equipment fleet with a new 30-tone EC300E excavator. You can read more about it on Agg-net.com below
Things are gathering pace at our Otley site now, after a couple of weeks of indifferent weather we are now at full steam ahead!!
This week we commence final trim on plots and roadways. Being built on a hill side in Otley the site incorporates some fairly intricate soil and crib retaining structures so it was decided we’d operate this site with predominately GPS equipped machines running mainly Trimble but also one Leica system. We’ve had no compatibility issues with the two systems and are now in a position to press on ahead and make the most of what we hope will be some sunshine!!